Laúca dam in Angola to produce 334 MW from 21 July
By the AFREEQUE newsroom, based on Rede Angola

The first generator at the Laúca dam in Angola is due to supply 334 megawatts of electricity from 21 July. Filling the reservoir, which began in March, had limited the power supply to Luanda, the Angolan capital, according to the Rede Angola media outlet.
The first generating unit of the Laúca hydroelectric complex, in Angola’s Malanje province, will begin producing 334 megawatts of electricity on 21 July, project director Elias Estêvão said, as cited by the Lusa news agency. The facility is built on the Kwanza River.
Testing of the transmission lines and substations is due to begin on 31 May on the section linking Laúca to the Capanda dam, also on the Kwanza. Filling of the Laúca reservoir began more than four months before the announced start of production, according to Elias Estêvão. The project is described as the largest public works project currently under construction in Angola.