Nouakchott emergency development programme reaches 96%
By the AFREEQUE newsroom, based on Alakhbar

The Mauritanian government says progress on the emergency programme dedicated to the development of Nouakchott has reached 96%. The announcement presents the project as nearly complete, without specifying in the excerpt what work remains or the delivery date, according to the Al-Akhbar newspaper.
The emergency programme for the development of Nouakchott, launched on 20 January 2025 by the Mauritanian government, had reached 96% completion by 31 July 2026, with 112% of the allocated time elapsed, the government announced in a statement issued after its meeting.
The programme made only three percentage points of progress overall between May and July 2026. The emergency programme aimed at extending access to essential services for local development, meanwhile, accelerated after a relatively slow start in its education and health components. Several of its components have reached a very high level of progress, according to the government.