Mauritius' Independent Review Panel invalidates CEB contract for 40,000 meter boxes
By the AFREEQUE newsroom, based on Defimedia

The Independent Review Panel (IRP) of Mauritius has invalidated a Central Electricity Board (CEB) contract for the purchase of 40,000 meter boxes, worth Rs 36.7 million. The title provided does not specify the grounds for, or the date of, this decision concerning this public procurement contract.
The Independent Review Panel (IRP), Mauritius' public procurement appeals body, has annulled the award by the Central Electricity Board (CEB), the state-owned electricity operator, of a contract worth 36.7 million rupees for the supply of 40,000 meter boxes to J. Annauth Construction Ltd. The IRP has ordered a re-evaluation of the bids, according to its decision.
The matter was brought before the panel by Resiglas Co. Ltd, the unsuccessful bidder, which had been challenging the procedure since 24 June 2026. The IRP considered that the offer from J. Annauth Construction Ltd did not sufficiently demonstrate the ‘local’ character of the goods proposed.