Uganda delays first oil production to June 2027
By the AFREEQUE newsroom, based on The Observer
The Ugandan government has set June 2027 as its new target for starting commercial oil production, after missing the July 2026 deadline. The delay extends a series of unmet timetables since exploitable deposits were discovered in the Albertine region, according to The Observer.
Uganda has pushed back its target for first commercial oil production to June 2027, after missing the July 2026 deadline. The government has already postponed the start of exploitation of deposits discovered in the Albertine basin, in the west of the country, several times.
In March 2026, the Petroleum Authority of Uganda (PAU), the body responsible for regulating the oil sector, had told the Parliament’s public accounts committee that first oil was expected by the end of July 2026. By that date, the East African Crude Oil Pipeline (EACOP), the pipeline intended to export Ugandan crude to the Tanzanian coast, was announced to be 81% complete.